Bid – Columbia Village Apartments Sidewalk Replacement Project

Sealed bids were requested by the Board of Regents of Washington State University, for the above referenced project.

Project Scope:

This project will upgrade the sidewalks, stairs, handrails, plaza area and drainage
throughout the Columbia Apartment Complex on the Pullman Campus. Contract
time shall be 90 days from Notice to Proceed to substantial completion.

Project Physical address: 540 SE Forest Way Pullman, WA 99164

Bid Estimate: $450,000 – $500,000

Alternate No. 1 – Provide New 6’ Concrete Sidewalk Along SE Forest Way.

  • Bid Results available below.

Point of Contact:
Project Manager: Kevin Poitra
Email: kpoitra@wsu.edu
Phone: 509-335-4206

In Person Pre-Bid Meeting:
Date and time: March 12, 2024 at 10:00 a.m.
Location: McCluskey Services Building, Room 190D

Bid Submittal Deadline:
Date and time: March 26, 2024, prior to 2:00 p.m.
By Email: contracts@wsu.edu
Or by Hard Copy: McCluskey Services Building, 2425 East Grimes Way, Pullman, WA

Bid Open:
Date and time: March 26, 2024, at 2:30 p.m.
Zoom Only: https://wsu.zoom.us/j/93694169581?pwd=WTdzU2tZSnZ5MGkxZnFOMzNhQ24vQT09
By Phone: 253-215-8782
Meeting ID: 936 9416 9581
Password: 329130

Bid Documents:
Advertisement
Project Manual
Drawings
Planholder’s List
Addendum 1
Bid Results