Sealed bids were requested by the Board of Regents of Washington State University, for the above referenced project.

Project Scope: Remove approximately 25,000 square feet of existing roof material and insulation. Construct new parapets around perimeter to allow for new insulation installation of R-38 minimum, and re-slope to existing drains. Install new EPDM roofing membrane. Substantial Completion shall be 90 Days from Notice to Proceed. Proposals must be based on this contract time.

Bid Estimate: $575,000.00 to $610,000.00

Deductive Alternate 1: Substitute TPO membrane system in place of EPDM membrane system.

  • Bid Results are available below. Thank you to all bidders.

Virtual Pre-Bid Meeting:
Date and time: July 27, 2023 at 10:00 a.m.
Zoom Only: https://wsu.zoom.us/j/92712377044?from=addon
By Phone: 253-215-8782
Meeting ID: 927 1237 7044

Bid Submittal Deadline:
Date and time: August 3, 2023 prior to 2:00 p.m.
By Email: contracts@wsu.edu
Hard Copy: McCluskey Services Building, 2425 East Grimes Way, Pullman, WA

Bid Open:
Date and time: August 3, 2023 at 2:30 p.m.
Zoom Only: https://wsu.zoom.us/j/94964653490?from=addon
By Phone: 253-215-8782
Meeting ID: 946 6465 3490

Bid Documents:
Advertisement
Project Manual
Drawings – REPLACED VIA ADDENDUM 1
Addendum 1
Addendum 2
Addendum 3
Addendum 4
Planholders List